Earned Value Calculator

Calculate CPI, SPI, CV, and EAC for schedule/cost control.

Earned Value Calculator evaluates project performance using planned value, earned value, actual cost, and budget at completion. Planned Value (PV) is the budgeted value of work that should have been completed by a point in time, Earned Value (EV) is the budgeted value of work actually completed, and Actual Cost (AC) is what has actually been spent. Cost Variance (CV) compares EV with AC, Schedule Variance (SV) compares EV with PV, Cost Performance Index (CPI) measures cost efficiency, and Schedule Performance Index (SPI) measures schedule efficiency. Values below 1.0 for CPI or SPI usually indicate unfavorable performance. EVM is useful for structured project control, but it depends on honest progress measurement and a meaningful baseline.

Permalink

Input guidance

Enter the values requested by the form.

How to use this tool

  1. Enter the values requested by the form.
  2. Run the tool and review the labelled output.
  3. Check assumptions, units, and edge cases before relying on the result.

EVM Inputs

Result

Cost variance (CV): -$15,000.00

Schedule variance (SV): -$25,000.00

CPI: 0.8636

SPI: 0.7917

Estimate at completion (EAC): $138,947.37

Estimate to complete (ETC): $28,947.37

Formula or method

How to interpret the result

Review note and limitations